TOTAL REPAIRS/REINSTATEMENT OF OZONE LEASE TO JUMIA NIGERIA admin October 10, 2020 Uncategorized MilestonesPlanned DatesActual DatesCommentsIntroduction of major stake holders and a brief meeting.14/08/202013/08/2020This was achieved according to plan.Review of project objectives with project team and paint colour agreement & commencement.25/08/2020(19/08/2020 Project starting date and completion02/09/202020/08/2020 HSE inductions and site policy awareness.19/08/201919/08/2019 WORK PROGRAM AND COMPLETION PICTURES OF THE SITE DURING AND AFTER PROJECT COMPLETION The state of the building before repairs and reinstatement of all the three floors State of the floors while items are being removed Completed staircase and final cleaning done and last floor completed with M & EP working Installed suspended ceilings and LED panel lights rotated POP screeding of all walls before painting Replaced all plumbing wares in the floors Painting work in commenced in all floors Completed all Electrical, plumbing, floor tiles, POP and Suspended ceiling work Completed all Electrical, plumbing, floor tiles, POP and Suspended ceiling work Laying of interlocking blocks Tiling of all staircases with Italian tiles Completed staircase tiling with hand railings Installed high security doors in each floor Deep cleaning of each floor Completed floors ready for use Completed staircase and final cleaning done and last floor completed with M & EP working Completed staircase and final cleaning done and last floor completed with M & EP working Post navigation Previous Previous post: MANTRAC PORT HARCOURT RESIDENTIAL RENOVATION COMPLETION REPORT 10th February, 2020Next Next post: IHS NEW OFFICE RENOVATION PROJECT