Menu Close

TOTAL REPAIRS/REINSTATEMENT OF OZONE LEASE TO JUMIA NIGERIA

MilestonesPlanned DatesActual DatesComments
Introduction of major stake holders and a brief meeting.14/08/202013/08/2020This was achieved according to plan.
Review of project objectives with project team and paint colour agreement  & commencement.25/08/2020(19/08/2020 
Project starting date and completion02/09/202020/08/2020 
HSE inductions and site policy awareness.19/08/201919/08/2019 

WORK PROGRAM AND COMPLETION

PICTURES OF THE SITE DURING AND AFTER PROJECT COMPLETION

The state of the building before repairs and reinstatement of all the three floors
State of the floors while items are being removed

Completed staircase and final cleaning done and last floor completed with M & EP working

Installed suspended ceilings and LED panel lights rotated

POP screeding of all walls before painting

Replaced all plumbing wares in the floors
Painting work in commenced in all floors

Replaced all plumbing wares in the floors

Painting work in commenced in all floors

Completed all Electrical, plumbing, floor tiles, POP and Suspended ceiling work
Completed all Electrical, plumbing, floor tiles, POP and Suspended ceiling work

Completed all Electrical, plumbing, floor tiles, POP and Suspended ceiling work

Completed all Electrical, plumbing, floor tiles, POP and Suspended ceiling work

Laying of interlocking blocks

Laying of interlocking blocks

Tiling of all staircases with Italian tiles

Completed staircase tiling with hand railings

Completed staircase tiling with hand railings

Installed high security doors in each floor

Installed high security doors in each floor

Deep cleaning of each floor

Deep cleaning of each floor

Completed floors ready for use

Completed floors ready for use

Completed staircase and final cleaning done and last floor completed with M & EP working

Completed staircase and final cleaning done and  last floor completed with M & EP working

Completed staircase and final cleaning done and last floor completed with M & EP working

Completed staircase and final cleaning done and  last floor completed with M & EP working