Menu Close

MANTRAC CAT OREGUN FENCE WALL PROJECT

 COMPLETION REPORT 21ST AUGUST, 2020

SOLIDEDGE Project Managers :  Operations and project team

Project Schedule Update 

Start date site 1 :               18th July , 2020

Planned completion :       20th August, 2020   

% Project completion :    100%

DISCLAIMER WARNING: This project was managed and supervised by SOLIDEDGE Facilities 100%, no third Party involved.  SEFM self performs all its projects.

Issues / Risks Identified

There was Stop work order from LAGOS Local Government for payment of Development levy and Renovation permit fee of NGN 450,000.00 which SOLIDEDGE Facilities paid agreed amount on behalf of MANTRAC. Other extortions from local council boys were recorded here and Nigerian Police force presence maintained law and order as work progressed.
Tools box talk remain our first assignment before commencement of each days task. No accident or incident that would cause injury or death recorded throughout the project work. Safety first was observed.

MANTRAC CAT NIGERIA BOUNDARY FENCE WALL  SCOPE COVERED TO COMPLETION

JOB IDTASK DESCRIPTION% CompletionStatus
M000Mobilization to site100Completed
CST001Setting out and site hoarding100Completed
RAR002Trench foundation to prepare for footing and ground beam100completed
RRW003Prepared formwork for the footing and beam100completed
INA004Arranged for pre-casting of the footing reinforcement100completed
POP005Applied blinding of the foundation to get footing toe100completed
REF006Placed the reinforcement for ground beam and matting of footing100completed
RPF007Formation of formwork for the footing and ground beam100completed
KC008Casting of footing100completed
FAP009Casting of ground beam and set the column with controlled height100completed
EF010Placing form work for the columns and cast100completed
MD011Allow for the erection of block walls to make up fence wall of 3,2m100completed
FSD012Cast pillars/column for the fence wall reinforcement100completed
BWR013Prepare formwork for capping and copping100completed
IDH014Casting of copping and placement of reinforcement for the copping100completed
IWH015Applied the security wire y-set for the installation100completed
PIE016Plastered the walls inside and outside  and rendered cement screed100completed
RIE017Removed all wall formations and backfill100completed
RIKB018Install security barb wire and demobilize site100completed
EW022Evacuation of all waste and other construction waste100completed
Casted ground beam with reinforced iron rods to allow block wall on it
Casted ground beam with reinforced iron rods to allow block wall on it
The fence wall on waterlogged area of the boundary wall
The fence wall on waterlogged area of the boundary wall
Block wall with columns
Block wall with columns
Plastering/rendering of completed fence wall
Plastering/rendering of completed fence wall
Rendering of the back of the fence walls
Rendering of the back of the fence walls
Plastered expansion joint
Plastered expansion joint
Pillar dressing experts rendering pillars/column will others plaster the block wall to standard
Completed rendering of boundary fence wall and pillars/columns to standard
Completed rendering of boundary fence wall and pillars/columns to standard
Completed both sides of the MNTRAC CAT  boundary fence wall of 16457.78SQ,Mters
Completed both sides of the MNTRAC CAT boundary fence wall of 16457.78SQ,Mters
Another fence phase preparation
Another fence phase preparation
Level accuracy checked with SOLIDEDGE MD on ground for zero accident and mistakes
Level accuracy checked with SOLIDEDGE MD on ground for zero accident and mistakes
Formation of copping and casting with accurate mix ratio
Formation of copping and casting with accurate mix ratio
Installation of Security barb wire  on all the fence walls
Installation of Security barb wire on all the fence walls
Completed fence wall with fence wire and wall screeded
Completed fence wall with fence wire and wall screeded