IHS NEW OFFICE RENOVATION PROJECT

COMPLETION REPORT 18th SEPTEMBER , 2020

SOLIDEDGE Project Managers :  Operations and project team

Project Schedule Update 

Start date site 1 :               10th September  , 2020

Planned completion :       18th September , 2020   

% Project completion :    100%

DISCLAIMER WARNING: This project was managed and supervised by SOLIDEDGE Facilities 100%, no third Party involved.  SEFM self performs all its projects.

Issues / Risks Identified

There was no issues and all work scope was covered as requested
Tools box talk remain our first assignment before commencement of each days task. No accident or incident that would cause injury or death recorded throughout the project work. Safety first was observed.

IHS COMMUNICATION NEW OFFCE RENOVATION SCOPE COVERED TO COMPLETION

JOB IDTASK DESCRIPTION% CompletionStatus
M000Mobilization to site100Completed
CST001Removal of old suspended ceiling100Completed
RAR002Dismantled old aluminum partition wall100completed
RRW003Install new suspended ceiling with all accessories100completed
INA004Installation of new electrical systems  wall sockets, raw and data100completed
POP005Rewire the floors for new office gadgets100completed
REF006Screed all the wall with POP and smoothened for painting100completed
RPF007Break walls and amend to fit in new office space according to plan100completed
KC008Replaced all old light fittings to LED Panel lights100completed
FAP009Installed new units of Panasonic Air conditioners in all the office spaces100completed
EF010Powered the Cooling systems and set according to space BTU reqd100completed
MD011Installed new stainless hand rails on all the staircases100completed
FSD012Fabricate and installed doors with frosting decadence100completed
BWR013Applied Satin finishes Quality paints to all the internal parts100completed
IDH014Applied weather shield acrylic quality paint for all the external walls100completed
IWH015Design windows and doors and applied  vitrified floor tiles100completed
PIE016Deep cleaning of all internal and external floors  of office100completed
RIE017Replaced all door locks and align all aluminum doors and partitions100completed
RIKB018Install AVS  to all raw power voltage sensitive equipment in offices100completed
EW019Evacuation of all construction waste and demobilizes100completed
Screeding the Wall with POP
Screeding the Wall with POP

POP Screeding on going

Installed new Suspended Ceiling and LED PANEL lights
Installed new Suspended Ceiling and LED PANEL lights