RENOVATION SCOPE COVERED TO COMPLETION.
JOB ID | TASK DESCRIPTION | % Completion | Status |
M000 | Mobilization to site | 100 | Completed |
CST001 | Construction of FOUR Septic Tanks, TWO each for Odoni 1 & Odoni 2 Property with all necessary connections and Civil works | 100 | Completed |
RAR002 | Removal of all the old asbestos roofs and Wood for the Main building and BQ, smaller units | 100 | completed |
RRW003 | Installation of New wood to raise the building to standard height before placing new Aluminum long span on the roof | 100 | completed |
INA004 | Installed New Aluminum long span on the roofs with Thunder arrestor | 100 | completed |
POP005 | Application of POP screed to the walls of the rooms and parlor to approved design, design and install Conies, ceiling screeding and POP | 100 | completed |
REF006 | General removal of electrical cables and Installation of new lines with approved cables and fittings | 100 | completed |
RPF007 | Replaced all plumbing lines with new pipes and fittings, installed WC and wash hand with bathing taps and fittings. | 100 | completed |
KC008 | Installation of Kitchen Cabinet with GRANITE top. | 100 | completed |
FAP009 | Supply and installation of Tiles on the walls of the Toilets and Bathrooms as approved | 100 | completed |
EF010 | Installation of Electrical fittings and fixtures on POP ceiling and Walls of the building with door bell | 100 | completed |
MD011 | Redesigned the Burglary proof for doors and widow to aid easy move in case of emergency | 100 | completed |
FSD012 | Fabricate and Installation of Security lights in approved positions in the premises | 100 | completed |
BWR013 | Supplied and Installation of Smoke Detectors in all the specified areas , Spray steps, table and shelves and doors | 100 | completed |
IDH014 | Installation of doors in the main house and generator house | 100 | completed |
IWH015 | Supply and installed Water Heater Systems in required area | 100 | completed |
PIE016 | Painted the internal and external area of all the buildings, fence, kerbs and security post | 100 | completed |
RIE017 | Re-screeded all the internal and external of the building and repainted again after the request for second finishing. | 100 | completed |
RIKB018 | Removed and reinstalled another Kitchen cabinet in the kitchen | 100 | completed |
ICSR 019 | Installed standard Curtains in the Sitting Room of the main building | 100 | Completed |
ICA020 | Removed the under-curtain veil of the curtain and replaced with another accessories | 100 | completed |
TCix021 | Cleaning of the internal and external area of the buildings | 100 | Completed |
EW022 | Evacuation of all wastes from roof and other construction waste | 100 | completed |